Kansas’ first Buc-ee’s has been pointing toward a spring 2027 opening, and the project’s general contractor has added more detail about what it will take to get there. Cleveland Construction says the build began in fall 2025 with a 20-month timeline.
That schedule offers a clearer look at the work behind the opening target, but it is not a grand-opening announcement. Buc-ee’s still lists Kansas City only as a 2027 opening, and the company has not announced a specific date for customers.

What changed since the last Kansas update
The previous update focused on Buc-ee’s recruiting pages, which tell management applicants that the Kansas City store is expected in spring 2027. Those listings remain active, but they do not explain how the construction itself is being managed.
The contractor’s project profile fills in that gap. According to Cleveland Construction, the travel center at 601 Village West Parkway is under construction and is being delivered on a 20-month timeline that began in fall 2025. The contractor identifies Buc-ee’s Ltd. as the owner and says it is managing the project.
A lot more than the store is being built
The work includes site development, earthwork, utility installation, concrete paving and landscaping. Cleveland Construction also says it is overseeing the project through structural construction and final interior finishes, meaning the schedule covers far more than putting up the main retail building.
Plans call for a 74,707-square-foot store with two fuel canopies and a 5,600-square-foot restroom area. The site sits near Interstate 70, Kansas Speedway and the Legends shopping district, where road and interchange work has also affected traffic during construction. Work around the interchange remains part of the broader access plan serving the future travel center.
The timeline supports 2027—but not a specific day
A 20-month construction plan beginning in fall 2025 broadly supports a 2027 completion window. It does not prove that the store will open the moment the contractor finishes, because inspections, equipment installation, inventory, hiring and training can all affect when the doors actually open.
Buc-ee’s current management job listings continue to use spring 2027, while the company’s public estimated-opening list gives the broader year 2027. Those two descriptions are compatible, but neither should be treated as a dated launch notice.
The important change is that Kansas fans now have both a company hiring window and a contractor’s construction schedule pointing in the same general direction. The store is not merely proposed or waiting for zoning—it is under construction, with a defined build plan and management recruiting underway. No cancellation or construction pause has been announced, though the opening date remains subject to change.